Concrete Volume Calculator
Choose a slab, a round column or a wall or footing, enter the sizes in feet, inches, yards, meters, centimeters or millimeters (a different unit for each size if you like), and add a waste allowance. You get the volume in cubic yards, cubic meters and cubic feet, and the number of 40, 60 and 80 lb bags. The bag yields are typical values that you can change to match the label on the bag you buy.
Concrete to order, with waste
1.36 yd³
Bags of mix
The yields below are rounded typical values, not exact: read the label of the bag you buy and change the number to match. Bags are rounded up.
123 bags (4,920 lb)
82 bags (4,920 lb)
62 bags (4,960 lb)
98 bags (4,900 lb)
How it works
- Pick the shape: slab, round column, or wall or footing.
- Enter each size and choose its unit.
- Set a waste allowance, 10 percent unless you know better.
- Read the volume to order, then adjust the bag yields to your brand and copy the summary.
What people use it for
Patio or shed slab
Length, width and thickness give the cubic yards to order from a ready-mix truck or the bags to carry home.
Fence posts and piers
Round holes, one diameter and depth, times the number of posts.
Footings and walls
Length, depth and width of a trench footing, or the height and thickness of a poured wall.
Questions
- How is the volume calculated?
- Slab: length × width × thickness. Wall or footing: length × height (or depth) × thickness (or width). Column: π × (diameter ÷ 2)² × height × number of columns. Every size is first converted to meters with the exact factors (1 ft = 0.3048 m, 1 in = 0.0254 m, 1 yd = 0.9144 m). One cubic yard is 0.764554857984 cubic meters, or 27 cubic feet. The waste allowance multiplies the result by 1 + percent ÷ 100.
- How much waste allowance should I add?
- Around 5 to 10 percent is common to cover spillage, an uneven sub-base and over-excavation. Use more if the ground is rough or the form is complicated. With ready-mix, running short costs more than ordering a little extra, so many people round up to the next quarter or half cubic yard.
- Are the bag yields exact?
- No. The defaults are rounded typical values for bagged concrete mix: about 0.30 cubic feet for a 40 lb bag, 0.45 for a 60 lb bag and 0.60 for an 80 lb bag. Yields differ by brand and mix, so read the label and type your own number. Bags are always rounded up to a whole bag.
- What does this not cover?
- It does not account for rebar, sloping or stepped forms, or a sub-base compacting. It gives the volume of a simple shape: for a complex pour, split it into several shapes and add the results. Check the plan with your supplier or engineer before ordering.