Task Dependency Critical Path Calculator
Write one task per line with its duration and the tasks it waits for. The page computes when each task can start and finish at the earliest, how much it can slip without delaying the project (its slack), the chain of tasks with no slack, and the total duration. A circular dependency or a prerequisite that does not exist is reported by name.
Total duration
5 h
Critical path: Design → Build.
| Task | Start | Finish | Slack | Critical |
|---|---|---|---|---|
| Design | 0 | 2 | 0 | Yes |
| Build | 2 | 5 | 0 | Yes |
| Buy materials | 0 | 1 | 4 | No |
How it works
- Write one task per line: task ; duration ; after A, B (leave the last part empty for a task that can start at once).
- Optionally change the unit shown next to the durations.
- Read the total duration and the critical path, then check the slack of every other task.
- Copy the summary or download the table as CSV.
What people use it for
Small projects and launches
Find the few tasks that decide the date of a release, a move or a renovation.
Event preparation
See which preparations can wait and which ones push back the opening.
Study and thesis plans
Check that a chain of reading, writing and review fits before a deadline.
Questions
- How are start and finish times computed?
- A task starts as soon as all its prerequisites are finished (time 0 if it has none) and finishes after its duration. The total duration is the latest finish. A backward pass from that date gives the latest start of each task without delay; the difference between the latest and the earliest start is the slack.
- What is the critical path?
- The chain of tasks with zero slack: if any of them slips, the whole project slips. When several chains have the same length, all their tasks are marked critical and one chain is written out.
- What does it do with errors?
- A task that waits for a name not in the list, a name used twice, or a circular dependency (A waits for B which waits for A) stops the calculation and the message names the tasks involved. Names are compared without caring about upper or lower case.
- What does it ignore?
- People and resources (it assumes everything that can run in parallel does), calendars, weekends, overlaps between tasks and uncertain durations. The list is limited to 200 tasks.